NYC upper east side floor leveling and structural girder repair
The apartment living room had a 5.5" slope from one side to the next spanning only 10'. We removed the entire living room floor and discovered that when the steam system was installed the girder was cut into in two locations. The Engineer recommended that the girder be sandwiched between two steel plates bolted through and through. After the girder was repaired we leveled the living room floor. There is a 5.5" step from the living room down into the kitchen, and a 1.25" step down into the bedroom.
|
Date: 10/19/2009
Owner: Trinity Development Group Inc
Size: 13 items
|
|
Living room floor north east corner
View of living room floor north east corner, view of dip in floor along the area where the girder and the kitchen header connect.
Date: 08/17/2009
Views: 211
Keywords: Trinity Development Group Inc, NYC licensed contractor, floor leveling, structural girder repairs, flooring, floor installation, floor refinishing, floor repairs, 3.25" white oak, steel repairs, wood girder repairs
|
Living room floor south east
View of living room floor south east prior to demolition
Date: 08/17/2009
Views: 208
Keywords: Trinity Development Group Inc, NYC licensed contractor, floor leveling, structural girder repairs, flooring, floor installation, floor refinishing, floor repairs, 3.25" white oak, steel repairs, wood girder repairs
|
Living room floor east wall
View of the living room floor above the deflected girder
Date: 08/17/2009
Views: 149
|
|
Living room floor north east corner slop
View of the living room floor highlighting the dip above the structural girder
Date: 08/17/2009
Views: 164
|
Living room girder steel installation
View of the living room steel installed around the girder
Date: 10/16/2009
Views: 161
|
Living room floor post demolition
view of the living room floor post demolition, floor leveling process with bridging and blocking
Date: 09/09/2009
Views: 190
|
|
Living room steam line
View of living room 1.25" steam line cut into structural girder
Date: 09/09/2009
Views: 131
|
Living room floor south east conrner
View of living room floor post demolition, view of leveling process, and exosed brick wall.
Date: 09/09/2009
Views: 198
|
Bedroom / Living room transition
View of the living room saddle, and the lower bedroom floor
Date: 10/15/2009
Views: 181
|
|
Living room floor north west corner
View of the living room floor north west corner, apartment door, kitchen entrance
Date: 10/15/2009
Views: 157
|
New living room floor with newly exposed brick.
New floor with high gloss oil poly
Date: 11/19/2009
Views: 90
|
living room floor finished
New floor with newly exposed brick wall
Date: 11/19/2009
Views: 93
|
|
view of living room step from kitchen
Small step into living room, truly shows the difference in height after the leveling process
Date: 11/19/2009
Views: 121
|
|
|
|